Short Reports: Memo and Letter Reports
Memo Reports
Memo Report is a short report used for circulation within departments.
The format is given below:
*********************************************************************************
Memo Report
*********************************************************************************
Memo Reports
Memo Report is a short report used for circulation within departments.
The format is given below:
*********************************************************************************
Memo Report
*********************************************************************************
Letterhead
To:
From:
Date:
Subject:
Body of the report
Signature
Now, the body of the report consists of a short introduction, main text and conclusions and recommendations.A memo is in fact an inter-office memorandum.
*********************************************************************************
Letter Report
*********************************************************************************
Letter Head
Date:
Inside Address
Subject:
Salutations
Body of the Letter
Complimentary close
Signature
Name
Designation
Enclosures
*********************************************************************************
Cover Page of A Report
*********************************************************************************
A Report on Green Campus
Prepared for
Mr LD Kala
Maintenance In-charge, ABC University , Faridabad, Haryana
by
Dr Arvind Gupta
Solar Energy Consultant, Green Buildings Pvt Ltd.
Approved by
Mr Subodh Mahanty
Chief of Energy Studies, Green Buildings Pvt Ltd
Green Buildings Pvt. Ltd. Noida
December 2, 2012
*********************************************************************************
Example of a Progress Report
*********************************************************************************
BPTP Builders, Faridabad
Progress Report
Date:____________
Name of the project:
Total work to be completed:____________________________
Work completed till date:______________________________
Work to be completed:_________________________________
Probable Date for Completion:____________________________
Suggestions: a) more funds, why and how much__________________
b) Extension of duration__________________________
c) Increased labour _____________________________
Remarks______________________________________________________
Signature
Designation
*********************************************************************************
*********************************************************************************
Cover Page of A Report
*********************************************************************************
A Report on Green Campus
Prepared for
Mr LD Kala
Maintenance In-charge, ABC University , Faridabad, Haryana
by
Dr Arvind Gupta
Solar Energy Consultant, Green Buildings Pvt Ltd.
Approved by
Mr Subodh Mahanty
Chief of Energy Studies, Green Buildings Pvt Ltd
Green Buildings Pvt. Ltd. Noida
December 2, 2012
*********************************************************************************
Example of a Progress Report
*********************************************************************************
BPTP Builders, Faridabad
Progress Report
Date:____________
Name of the project:
Total work to be completed:____________________________
Work completed till date:______________________________
Work to be completed:_________________________________
Probable Date for Completion:____________________________
Suggestions: a) more funds, why and how much__________________
b) Extension of duration__________________________
c) Increased labour _____________________________
Remarks______________________________________________________
Signature
Designation
*********************************************************************************
No comments: